Aug 16, 2018

The Rise August Construction Update

If you've driven pastThe Rise Condominiums lately at 300 Centre Street you may have noticed some changes! Phase 1 of The Rise is continuing to make strides as we look forward to first possession dates in November 2018. Read on to find out what's been happening.


Exterior

  • Building commercial wrap installation completed
  • Building water membrane install completed
  • Patio doors and windows are installed
  • Main roof install 100%
  • East and west elevation brick and tyndall stone completed
  • EIFS systems underway



Parkade

  • All concrete work completed
  • Electrical rough in completed
  • Plumbing rough in completed
  • Sprinkler rough in completed
  • Masonry walls 100% complete

 

1st Floor

  • All concrete work completed
  • Interior steel stud framing completed
  • Exterior steel stud framing completed
  • Exterior sheathing installed
  • Window install completed
  • Patio door completed
  • Electrical rough in completed
  • Plumbing rough in completed
  • Display suite and presentation center open for viewing

 

2nd Floor

  • Exterior steel stud framing completed
  • Exterior sheathing completed
  • Interior walls completed
  • Windows installed
  • Pumbing rough in completed
  • Electrical rough in completed
  • HVAC rough in completed
  • Board and taping underway

 

3rd Floor

  • Exterior steel stud framing completed
  • Exterior sheathing completed
  • Windows installed
  • Interior walls completed
  • Plumbing rough in underway
  • Sprinkler rough in underway
  • HVAC rough in completed
  • Drywall board completed
  • Taping drywall underway

 

4th Floor

  • Electrical rough in completed
  • Plumbing rough in underway
  • HVAC rough in completed
  • Insulation/vapor barrier install completed
  • Boarding and taping underway
  • Suite priming underway

 

5th Floor

  • Drywall complete
  • Drywall taping completed
  • Exterior steel stud framing completed
  • Exterior sheathing completed
  • Windows installed
  • Interior walls completed
  • Plumbing rough in underway
  • Electrical rough in underway
  • HVAC rough in underway
  • Bulkhead framing completed

 

6th Floor

  • Exterior steel stud framing completed
  • Exterior sheathing completed
  • Windows installed
  • Interior walls completed
  • Plumbing rough in completed
  • Electrical rough in completed
  • HVAC rough in completed
  • Bulkhead framing completed
  • Drywall taping complete
  • Drywall complete
  • Suite priming complete
  • Gypcrete topping complete

 

7th Floor

  • Exterior steel stud framing completed
  • Exterior sheathing completed
  • Ceilings are all dry walled
  • Interior walls completed
  • Plumbing rough in completed
  • HVAC rough in completed
  • Electrical rough in completed
  • Sprinkler rough in completed
  • Drywall complete
  • Drywall taping complete
  • Suite priming complete
  • Gypcrete topping complete
  • Flooring install underway
  • Kitchen install complete
  • Counter top install underway
  • Backsplash install underway

 

The Rise Presentation Centre

If you're interested in seeing for yourself, come by our Presentation Centre and we'd love to give you a tour. We're open Tuesday/Thursday from 2-7pm and Saturday/Sunday from 12-5pm, or you can always book a private tour with our team. www.therisecondos.ca